Dorset Highways Public Private Partnership
General Scope:
Hanson Contracting carries out carriageway resurfacing and highway maintenance schemes in partnership with Dorset Works Organisation.
Following award in 2002 the parties established a partnership steering board and set of aligned objectives for the partnership. This commitment to work in partnership was cemented in 2003 with the signing of a formal partnering charter at the House of Lords.
Early Contractor Involvement between all parties on the major schemes element of the scope of work has resulted in considerable benefits in cost and time. Hanson has worked with Dorset County Council through the condition surveys and structural maintenance team meetings to ensure programme and strategy issues are achieved wherever possible. This has resulted in reduced management and supervision costs on all of the schemes procured through the Partnership.
Reciprocal working has been a key feature of the partnership with Hanson utilising Dorset Works Organisations sign shop, vehicle workshops, grounds maintenance and highway maintenance departments.
Dates: April 2002 - March 2009
Form of Contract: Bespoke Partnership Contract
Value: £12,500,000
Innovation:
• First Highways Public Private Partnership in England
• Reciprocal working arrangements
• Use of specialist sidewinder paving machines to improve quality and efficiency in haunch repairs
Public Relations:
• Excellent Public satisfaction feedback scores
• Individual response and notification of improvement action provided to any dissatisfied customers
• Focus on facilitating access for ‘to door’ council services within rural communities
Sustainability:
• Use of in-situ recycling on schemes such as the A338 (14,000m2 of base course recycled in-situ)
• Recycling facility established at local quarry
Achievements:
• Awarded demonstration status by the Constructing Excellence Forum
• £800,000 in Reciprocal trading
• Zero RIDDORS in 350,000 man hours (7 years)
• Zero Environmental incidents in 7 years
• Over 250,000 tonnes of Asphalt laid
• Achieved all recycling targets
• Excellent Customer Satisfaction ratings
• Right First Time (0.1% remedial works)