Constructing the Aquaflow ThermaPave® geothermal system

The geothermal pipes are the only difference in pavement composition from the standard Aquaflow system. This means the extra cost and alteration to the design in minimal. The pipes are simply back filled after covering with 5mm gravel.

The geothermal pipes must be heat welded together and pressure tested when installation is complete. The pipes have a lifelong guarantee of 50 years.

     
Fitting welded membrane     Lay and compact 6mm pipe bedding stone   Heat weld the horizontal collector pipes
 
Pressurise the system Install and compact the graded sub-base stone Compact for laying course
   
Trim Inbitex® Geotextile to finished paving level  Lay the Aquaflow/Aquasett permeable paving Finally brush in the 3mm grit surface dressing